Last updated: September 21, 2026

ERCOT Interconnection Queue for Data Centers, Explained

Texas is rewriting how large loads connect to ERCOT. Senate Bill 6, signed in June 2025, directed the Public Utility Commission of Texas and ERCOT to build a formal large-load interconnection framework, and a draft rule now working through the PUCT would apply detailed standards — security deposits, site-control proof, curtailment obligations — to any new or expanding load of 75 MW or more.

⚡ TL;DR — ERCOT Large-Load Interconnection in 2026

  • • SB6 (June 2025): directed the PUCT and ERCOT to build a large-load interconnection framework and expand curtailment authority
  • • Proposed rule, 16 TAC §25.194: would cover new/expanding loads of 75 MW or more, with final adoption required no later than December 31, 2026
  • • Cost gate: draft terms include a $50,000-per-MW security deposit and interconnection fee
  • • Site-control gate: customers must show a deed, purchase option, or lease — and disclose parallel affiliate requests — before ERCOT opens a study
  • • Queue status: roughly 438,000 MW of requests reported as of June 2026; study progress paused during a governor-directed audit that began August 3, 2026

Why Texas Passed Senate Bill 6

ERCOT is unusual among US grid operators for reasons our Texas guide covers in more depth: it's a deregulated, single-state grid, largely outside FERC's direct jurisdiction, which lets large buyers sign power purchase agreements straight with generators. That same structure created two problems as data center and crypto-mining demand grew fast. First, large loads were increasingly co-locating with existing power plants — a move that can look, from the grid's perspective, like removing that generation from serving everyone else. Second, ERCOT had limited formal authority to curtail large loads the way it can curtail other resources during an emergency, which matters a great deal in a state that lived through the February 2021 winter storm.

Signed by Governor Abbott on June 20, 2025, SB6 gave the PUCT and ERCOT a legislative mandate to fix both: build a real interconnection framework for large loads and strengthen curtailment authority over them, including co-located projects. What follows below is the rule the PUCT has been building since — not yet final, but far enough along that landowners and brokers with Texas parcels should understand the shape of it.

The Proposed 75 MW Rule

On March 12, 2026, the PUCT proposed 16 Texas Administrative Code §25.194, a rule establishing detailed interconnection standards for new and expanding electric loads of 75 MW or greater in ERCOT territory — the threshold that captures essentially every hyperscale or large colocation data center project. Public comments on the draft closed April 17, 2026, and the PUCT has committed to finalizing any resulting rule changes no later than December 31, 2026. Until that happens, a project moving through the queue today is doing so under rules still in motion, which is worth flagging to any buyer who cites a specific timeline as settled fact.

The draft's cost provisions are the part most likely to affect deal economics directly: a proposed $50,000-per-MW security deposit and interconnection fee, meaning a 300 MW data center request would carry a $15 million deposit under the terms as drafted. That's a meaningful change from how large-load interconnection has typically worked in ERCOT, where formal financial commitments at this scale, this early in the process, haven't been standard.

The New Gate Before a Study Even Starts

Perhaps the most consequential change for landowners specifically: under the draft rule, a customer has to execute an intermediate agreement with the relevant transmission provider before ERCOT will begin an interconnection study at all. That agreement requires demonstrating site control — a deed, a purchase option, or a signed lease, not a letter of intent — and disclosing whether the same company or its affiliates have filed parallel or similar interconnection requests elsewhere in ERCOT territory.

That second requirement is a direct response to a pattern regulators had flagged: developers filing duplicate or speculative requests across multiple sites to hold a place in line while they decided where to actually build, which inflates the reported queue and makes it harder for ERCOT to plan real capacity. For a landowner, the practical read is that a serious buyer now needs clean, demonstrable site control earlier in the process than before — which is one more reason a parcel with a single owner and no title complications moves faster through diligence. See our land due diligence checklist for what that documentation typically involves.

Site Intake

Have land in ERCOT territory near substations or transmission?

Submit it for a confidential data center site review. No obligation.

Your information is reviewed privately. We only use submissions to evaluate potential fit and relevant opportunities.

438,000 MW and the August 2026 Audit

ERCOT reported roughly 438,000 MW of large-load interconnection requests in its queue as of a June 2026 update — a figure that, on its face, is several times more capacity than ERCOT's entire current generation fleet, a strong signal that much of the queue is speculative, duplicative, or attached to projects that will never actually break ground. On August 3, 2026, Governor Abbott directed the PUCT and ERCOT to audit every project in the large-load queue, requiring each to disclose its funding sources, power generation procurement plans, water usage, community engagement record, and ownership structure.

Study progress on the queue has been paused while that audit runs. For anyone tracking a specific Texas project, that means published queue positions and timelines from before August 2026 should be treated as provisional, not current — confirm status directly with ERCOT or the transmission provider involved. The audit itself is also a useful signal about where Texas regulators expect the queue to shrink: projects that can't document real funding, water access, and community engagement are the likeliest candidates to be dropped once the audit concludes, which should thin the queue toward more credible, better-capitalized projects over time.

Curtailment and Co-Located Projects

SB6's curtailment mandate has already been tested. The PUCT has affirmed curtailment authority over co-located data centers in its first net-metering case decided under the new law, meaning a large load paired with onsite generation doesn't automatically sit outside ERCOT's emergency curtailment framework simply because it isn't drawing full grid power at all times. That matters for a specific kind of project — one that pairs a data center with dedicated gas or renewable generation on the same site — that had sometimes been pitched as a way to sidestep grid constraints entirely. See our behind-the-meter power guide for how that self-supply model generally works, and confirm current ERCOT curtailment terms with counsel before assuming a co-located project is exempt.

ERCOT vs. PJM and MISO on Large-Load Reform

Texas's approach stands apart from how other grid operators have handled the same underlying pressure. PJM's reforms came from its own Board of Managers and FERC-approved tariff filings — see our PJM interconnection guide — while ERCOT's changes are being driven directly by the Texas legislature and the PUCT, a state regulatory process rather than a FERC docket, since ERCOT sits mostly outside FERC's jurisdiction as a single-state grid. MISO, covering a dozen Midwest and Plains states, is pursuing its own separate large-load framework; see our MISO interconnection guide for how that compares.

The takeaway for anyone evaluating land across state lines: a rule or timeline you've heard about from one grid operator's territory does not transfer to another. ERCOT's site-control gate and security-deposit structure are Texas-specific responses to Texas-specific political and reliability pressure — useful context, but not a preview of what MISO or SPP will eventually adopt.

What This Means for Texas Landowners

None of this changes what makes a Texas parcel fundamentally attractive to a data center buyer — substation and transmission proximity, water access, and clean title still matter as much as they ever did. What's changed is when in the process a buyer needs to prove those things. Under the draft rule, site control has to be demonstrable before ERCOT will even open a study, which means a landowner who can offer a straightforward deed or option, with no competing claims or unresolved mineral rights or title issues, is a meaningfully easier yes for a developer trying to clear that gate quickly.

Water documentation is worth flagging separately given its place in the August 2026 audit requirements — see our water rights guide for what to have ready. A parcel that can answer the funding, water, and community-engagement questions the audit is asking of developers — even informally, before a specific buyer arrives — is better positioned once ERCOT's queue starts moving again.

Frequently Asked Questions

What is ERCOT's large-load interconnection process?

It's the engineering study and approval process a data center or other large electric load must clear before ERCOT and the local transmission provider will connect it to the grid. Texas has been rewriting this process since Senate Bill 6 became law in June 2025, and as of this writing the Public Utility Commission of Texas is finalizing a formal rule — 16 TAC §25.194 — that would apply detailed interconnection standards to new or expanding loads of 75 MW or more, rather than leaving the process to informal utility practice.

Why did Texas pass Senate Bill 6?

To address two problems the legislature saw arising from the pace of data center and crypto-mining growth: the risk of large loads co-locating with existing generation in ways that effectively remove that generation from serving the broader grid, and ERCOT's limited ability to curtail large loads during emergencies the way it can curtail other resources. SB6 gave the PUCT and ERCOT a mandate to build a large-load interconnection framework and clearer curtailment authority rather than handling each project as a one-off negotiation.

How much does the proposed rule require in fees and deposits?

The draft rule circulated in early 2026 includes a security deposit and interconnection fee structured at $50,000 per MW of requested capacity, plus new upfront requirements before ERCOT even opens a study — including proof of site control (a deed, purchase option, or lease) and disclosure of any parallel interconnection requests filed by the same company or its affiliates. None of this is final until the PUCT adopts the rule, which the agency has said will happen no later than December 31, 2026.

Is the ERCOT large-load queue currently moving?

Partially. ERCOT reported roughly 438,000 MW of large-load interconnection requests in its queue as of a June 2026 status update — far more capacity than the grid could plausibly serve, a sign the queue includes significant speculative or duplicate requests. On August 3, 2026, Governor Abbott directed the PUCT and ERCOT to audit every project in that queue, requiring disclosure of funding sources, power procurement plans, water usage, community engagement, and ownership. Processing of the underlying study has been paused while that audit runs, so timelines for any specific project should be confirmed directly with ERCOT rather than assumed from pre-audit estimates.

Can co-located data centers avoid ERCOT curtailment under SB6?

No — the Public Utility Commission of Texas has affirmed curtailment authority over co-located data centers in at least one case decided under SB6's new net metering rules, meaning a large load paired with onsite generation doesn't automatically get to sit outside ERCOT's emergency curtailment framework. The exact terms depend on how a given project is structured and interconnected, so this is a point to confirm with counsel or ERCOT directly rather than assume from a general co-location arrangement.

Site Intake

Own or represent land in ERCOT territory?

Submit it for a confidential data center site review. No obligation.

Your information is reviewed privately. We only use submissions to evaluate potential fit and relevant opportunities.